Design
KCM AD
– Complete engineering and “Turn key” execution, part Electrical and Automation of New Lead Plant, 2012-2014
– Complete engineering and “Turn key” execution, of Substation 20, 2014
– Complete engineering for reconstruction of Substation 20, 2014
ASAREL MEDET AD
– Modernization of 20 kV and 6 kV switchgear and control room of Kaleto 2
Pumping Station
SOFIYSKA VODA AD
– Detailed design for modernization of 110/6 kV Kubratovo Substation
MARITSA IZTOK 2 TPP
– Modernization of 0.4 kV substation in Make-up Water Pumping Station
– Detailed design for replacement of LV distribution swithboards Station Services
ELATSITE MED AD
– Detailed design for complex construction of Crushing Unit No. 3
and ore transportation
NEOCHIM AD
– Project for replacement of protection relays in 110 kV switchyard
SIEMENS EOOD
IMPO– Design, manufafacture, delivery and commissioning of 4 pcs. MCC type SIVACON S8 in MONDI Stamboliyski EAD, 2015
STOMANA INDUSTRY AD
– Projects for reconstruction of LV substation No. 10, pumping station No. 1
and Scrap Workshop
WATER SUPPLY AND SEWAGE, Varna
– Project for modernization of 20 kV and 0.4 kV distribution switchgear
in Nikola Vaptsarov Pumping Station
RUSE TPP AD
– Project for replacement of generator protection relays 110 kV
ACTAVIS, Troyan
– Detailed design for a new 20/0.4 kV substation
BUILDING DEVELOPMENT HOLDING EOOD
– Full detailed electrical part design for building of Haskovo
Waste Water Treatment Plant