Turnkey projects
OFFERING AND DESIGN
Team of highly qualified experts with full design capacity and experience, acquired in the largest industrial and energy enterprises in Bulgaria.
Work with specialized software:
AutoCAD Electrical, ePLAN, Simaris Design, Simaris SIVACON.
Staff employed:
Sofia – 10
Dobrich – 5
Varna – 2
SPECIFICATIONS AND DELIVERYECIFICATIONS AND DELIVERY
Three warehouses for facilities, materials
and equipment in: Sofia , Dobrich, Varna
Staff employed:
Sofia – 7
Dobrich – 3
Varna – 1
DESIGN DEVELOPMENT AND MANUFACTURESIGN DEVELOPMENT AND MANUFACTURE
Preparation of design manufacture
There are three separated production workshops: mechanical, electrical assembly and workshop for assembling and dispatching. Work area: 3144 sq. m.
Staff employed (Dobrich):
Management – 4
Constructors – 8
Manufacture – 40
Administration – 5
FACTORY TESTING
Function testing in testing station – final control in ELIA Electrical Equipment Plant in Dobrich, equipped by SEBA KMT – Germany.
Staff employed:
Dobrich – 3
DELIVERY ON SITE AND INSTALLATION
Own transport vehicles: 17 vans and three trucks.
Trained teams to implement the assembly activities on site.
Staff employed:
Sofia – 3
Dobrich – 6
ADJUSTMENT AND COMMISSIONINGUSTMENT AND COMMISSIONING
ELIA Control Body
Mobile laboratory, equipped with the last generation measuring and testing facilities.
Staff employed:
Sofia – 5
Dobrich – 2
MAINTENANCE AND SERVICE
Six-seats service vehicle with a double room, equipped with tools, stand for busbar processing and personal protective equipment for repair on site at the client.
Staff employed:
Sofia – 2
Dobrich – 3
KCM AD
In the period 2012-2014, ELIA Plc designed, supplied, installed and put into operation Electrical and Automation equipment and systems of the New Lead Plant (NLP) at KCM AD – Plovdiv. Partner and subcontractor for the Automation system was SAT EOOD. The New Lead Plant at KCM AD is the largest investment made by Bulgarian company for the last 25 years in the heavy metallurgy in Bulgaria. The investment amounts to over BGN 200 million.
PRINT HOUSE BULGARIA – EAST – VARNA
Full implementation of the electrical power part of the largest print house on the Balkans,including:
- 20/0.4 kV substation
- External power supply and modernization of 20 kV distribution switchgear in the 110/20 kV power substation
- Main low voltage switchboards
- Power and low voltage electrical installations
- Systems for back-up and emergency power supply
WATER SUPPLY AND SEWAGE, Varna
Manufacture, installation, commissioning, adjustment and putting into operation
of equipment for Nikola Vaptsarov Substation, including:
- Modernization of 20 kV switchgear
- New main LV distribution switchboards
Manufacture, installation, commissioning, adjustments and putting into operation
of equipment for Vladislavovo Substation
ТPP ENEL MARITSA IZTOK 3
Desulphurization (FGD) Plant – a turnkey project, including:
- Manufacture, installation, adjustment and commissioning of 6 kV substations
- Main switchboards – type MCC 50 panels
SOFIYSKA VODA AD
Modernization of 110/6 kV Kubratovo Substation – turnkey project – manufacture,
installation, commissioning, adjustment and putting into operation, including:
- Complete RETROFIT (primary and secondary commutation) of 6 kV switchgear
- Control room – design, manufacture and commissioning of new relay protection
and control switchboards, operating current and SCADA
OILTANKING
- Supply and installation of
- 20 kV distribution switchgear
- LV distribution switchboard and diesel generator
- Facilities and networks on site
- Design, installation, adjustment and commissioning of modular 20 kV SF6 switchgear
MONTUPET BULGARIA EOOD
Plant for spare parts for automobile industry
– A turnkey project, including manufacture, installation, commissioning, adjustment and putting into operation of:
- Main substation 20 kV
- Six factory substations 20/0.4 kV, 2500 kVA
- Lightning, power and low voltage installations
MALL VARNA
Manufacture, installation, commissioning, adjustment and putting into operation of:
- External power supply 20 kV
- Three medium voltage substations
- Six dry transformers
- More than 500 main and distribution switchboards
BAD GRANITOIDS AD
Cascade Rila
- Complete modernization of four hydropower plants (Rila, Pastra, Kamenitsa, Kalin) – 110 kV and 60 kV switchyard, 20 kV and 5 kV switchgear and control room
ELATSITE MED AD
Crushing Unit KET 3 and conveyor belts
- Complex equipment Electrical and Automation part
- Extension of existing MV substation
- Low voltage substation and MCC
- Automation and a new dispatch center
Investor Thyssen Krupp, Germany
DYUNI RESORT COMPLEX
- Manufacture, delivery and commissioning of three new substations 20/0.4 kV
- Main low voltage switchboards
- Six dry transformers
ASAREL MEDET AD
- Turnkey energy project for overall modernization of the plant according to
Energy Program SRK – USA. More than 400 panels type MCC 0.4 kV - Modernization of Main lowering substation 110/6/6 kV